Feb. 5 to Feb. 11 Project Update

Hello All,

Our upcoming week will consist of City of Seattle inspections.  Our sub contractor traffic will diminish significantly to only a pick up crew and inspectors.  At the end of the week we will be starting our insulation phase.

Insulation installation will take a couple of weeks and the local impact will consist of a larger box truck parked on our lot to deliver and install the insulation.

As an upcoming note: we will be stocking drywall starting on Friday, February 17th and starting again on Monday the 20th (Not including the weekend).  There will be a few days which we will be unloading trucks of drywall, which will delay traffic.

Thank you for you patience in this process.

One thought on “Feb. 5 to Feb. 11 Project Update

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s