June 1st to June 9th project update

Hello All,

As previously notified, we are on track to reinstall our sidewalk and curb in front of our project, as well as the replacement of the driveway strip on the east side of our building.  Our concrete truck is scheduled to start at 11:00 am tomorrow, Thursday the 1st.

Our landscaper will be starting early next week.

As always, thank you for your patience with the process.

May 28 to June 4 Project Update

Hello All,

I hope everyone has a good Memorial Day Weekend.

During the upcoming week we hope to complete our concrete work and then start our landscape irrigation.

On Thursday June 1st we will be replacing the sidewalk and curb.  We are also replacing the open portion of driveway on the east side of our building.  This will complete our concrete work.

Next week we are also starting our landscape work, working in the back yard first and then the the front yard after the concrete it placed.  The bulk of the landscape and irrigation will take about 2 weeks, but the plantings wont be installed until the end of June.

On the inside, we are continuing with the cabinets, counters and flooring.

As always, thank you for your patience.

May 16th Project Update

Hello All,

Regarding our noted concrete pour dates – Wednesday the 17th we will be replacing the street panel in front of our building as previously communicated.  Starting about 8:00 am will be removing the existing panel and starting about 12:30 replacing it.

Due to the weather conditions, we are rescheduling our on site sidewalks to Friday the 19th.  Our curb and remaining sidewalks will still be installed next week.

Thank you.

May 10 Update

Updated notes regarding our concrete pour next week.

On next Wednesday we will pour our site sidewalks, the driveway strip, and the necessary replacement street areas in front of our lot.  Please expect traffic delays and detours.

Also, we intend to pressure wash the driveway to the east of our property in an effort to clean off the paint and waterproofing stains, dirt and debris.  We will do so asap, meaning as soon as practical, but in the near future.

Thank you.

May 8 to 19th Project Update

Hello All,

We are moving forward toward completion and our next week will be very busy.  Here is what is coming up.

Exterior-

Thursday and Friday we will be final grading and backfilling our front yard.  We will have a small tractor in the front yard moving and loading soil to needed locations, and grading for sidewalk installation.

Next Wednesday the 17th we will be pouring our on-site sidewalks and the portion of driveway on the east side of our building (weather permitting).  We will have a concrete pump truck, and the total pour will last most of the day.

Shortly after that, maybe Friday the 19th, we will be replacing a portion of the street, and placing our new sidewalk in front of our property.  Early the following week we will pour the curbs in front of our building and then be finished with concrete 🙂

Interior-

We are finished with drywall and Thursday and Friday the inside walls will be painted.  On this coming Monday and Tuesday we will be placing our gyp-crete inside the building.  This is basically pouring concrete on the wood floors for fire safety.  Starting on next Thursday we will be delivering cabinets for the units.

As always, thank you for your patience.