Hello All,

We are on the final push toward completion.  We are hoping to have our inspection process wrapped up by the end of July.

Today I was made aware of a parking issue by the landscaping truck.  I will discuss deliveries with the drivers and contractors again.  Once a delivery is completed we will have the trucks removed as quickly as prudent.

That said, we will be having many deliveries of appliances, materials, etc over the coming weeks.  We will do our best to keep close to the curb, off load the product and have the delivery truck removed asap.  This Monday morning we will have such a delivery.

Regarding the planting strip on the south side of our sidewalk, we were required to install this area by SDOT.  We requested a variance, and were rejected.  I am aware that neighbors have also requested a variance of this SDOT requirement, these were also refused.  This is what we have to work with and we will do our best to park as tight as possible to the curb, and will absolutely abide by all Seattle laws.

As always, thank you for your patience in the process.  We are almost done!

One thought on “Week of 7-1 to week of 7-16

  1. On a separate note, please let the person who leads the building tours know that no, we do NOT have “plenty of street parking available”. Truth in advertising, please – you need to tell them that tennants are NOT to own a car – your people promised us there would be “no new vehicles”. Truth in advertising, indeed. Or was it fake news, as we all knew it would be?

    Like

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s