May 17 concrete confirmation

Good morning.

I am confirming our street panel repair today.

Tomorrow we will have our cabinet delivery.  This will consist of a large moving trailer parked in front of our project most of the day.

Lastly, the on site sidewalk pour is set for Monday.

Thank you.

 

May 16th Project Update

Hello All,

Regarding our noted concrete pour dates – Wednesday the 17th we will be replacing the street panel in front of our building as previously communicated.  Starting about 8:00 am will be removing the existing panel and starting about 12:30 replacing it.

Due to the weather conditions, we are rescheduling our on site sidewalks to Friday the 19th.  Our curb and remaining sidewalks will still be installed next week.

Thank you.

May 10 Update

Updated notes regarding our concrete pour next week.

On next Wednesday we will pour our site sidewalks, the driveway strip, and the necessary replacement street areas in front of our lot.  Please expect traffic delays and detours.

Also, we intend to pressure wash the driveway to the east of our property in an effort to clean off the paint and waterproofing stains, dirt and debris.  We will do so asap, meaning as soon as practical, but in the near future.

Thank you.

May 8 to 19th Project Update

Hello All,

We are moving forward toward completion and our next week will be very busy.  Here is what is coming up.

Exterior-

Thursday and Friday we will be final grading and backfilling our front yard.  We will have a small tractor in the front yard moving and loading soil to needed locations, and grading for sidewalk installation.

Next Wednesday the 17th we will be pouring our on-site sidewalks and the portion of driveway on the east side of our building (weather permitting).  We will have a concrete pump truck, and the total pour will last most of the day.

Shortly after that, maybe Friday the 19th, we will be replacing a portion of the street, and placing our new sidewalk in front of our property.  Early the following week we will pour the curbs in front of our building and then be finished with concrete 🙂

Interior-

We are finished with drywall and Thursday and Friday the inside walls will be painted.  On this coming Monday and Tuesday we will be placing our gyp-crete inside the building.  This is basically pouring concrete on the wood floors for fire safety.  Starting on next Thursday we will be delivering cabinets for the units.

As always, thank you for your patience.

 

 

April 28 to May 8th Project Update

Hello All,

We are on track toward completion per my last post.  I anticipate concrete trucks on site next Tuesday or Wednesday for the retaining wall footings in the front yard, and maybe the wall portion at the end of the week.  We will then be pouring our onsite sidewalks following that.  When the onsite sidewalks are completed, we will wrap up the concrete phase with the street repairs, curb and sidewalk.

Once the curb and gutter are installed, we will begin the landscape installation

I am anticipating the exterior to be generally completed by mid June.

On the inside, we are completing the drywall for the next week and a half, then moving into the interior finish trades.

Thank you all for your patience.

4/21 to 4/30 Project update

Hello all.

We have a forecasted sunny day!  Yea.  Today, 4/21, we will have a large crew of painters attempting to complete the bulk of the exterior paint of our project.  After today we can expect some touch up requirements after the landscape is wrapped up.

In the near future we can expect:

4/24 and 4/25 – final exterior grading

4/26 to 5/10 various concrete pours as we complete the remaining retaining walls and sidewalks

5/15 Irrigation and landscape installation

On the interior we will be continuing the drywall phase for 2 more weeks.

Thank you for your patience in the process